LET Reviewer: Inverse Proportion – Workers and Days Mathematics Problem with Answer and Rationale

 

LET General Education Mathematics reviewer illustrating an inverse proportion problem involving eight workers completing a job in four days.

LET GENERAL EDUCATION REVIEWER

INVERSE PROPORTION

Workers and Days | Practice Question | Answer and Rationale

SLRC — Board Exams Made Easy.

Introduction

Mathematics is an important component of the General Education portion of the Licensure Examination for Professional Teachers (LET/LEPT). Examinees must understand mathematical relationships and develop problem-solving skills to answer different types of word problems.

One important topic in Mathematics is inverse proportion. This concept is commonly applied to problems involving workers and time, machines and production, speed and travel time, and other situations where one quantity decreases as another increases.

In this LET practice question, we will learn how to calculate the number of workers required to finish a particular job within a shorter period using the concept of inverse proportion.

Table of Contents

LET Practice Question

Question:

To finish a certain job in 6 days, 8 workers are needed. If it is required to finish the same job 2 days earlier, how many workers have to work?

A. 12

B. 10

C. 6

D. 14

Correct Answer

A. 12 workers

Twelve workers are needed to finish the same job in 4 days, assuming all workers have equal productivity.

Detailed Rationale

To solve this problem, we need to understand the relationship between the number of workers and the number of days required to complete a fixed amount of work.

Given:

  • 8 workers are needed.
  • The original completion time is 6 days.
  • The job must be completed 2 days earlier.

Step 1: Determine the required number of days.

The job must be completed 2 days earlier than the original 6-day schedule.

6 days - 2 days = 4 days

Therefore, the required completion time is 4 days.

Step 2: Identify the mathematical relationship.

Since the amount of work remains the same, the number of workers and the number of days are inversely proportional, assuming equal working efficiency.

We use the formula:

Workers × Days = Constant Work

8 × 6 = x × 4

Step 3: Solve for the unknown number of workers.

First, multiply the original number of workers by the original number of days.

8 × 6 = 48 worker-days

Next, divide the total worker-days by the required number of days.

x = 48 ÷ 4

x = 12 workers

FINAL ANSWER: 12 WORKERS

The correct choice is Letter A.

Analysis of All Choices

Option A: 12 – CORRECT

Twelve workers are needed to finish the job in 4 days. The total work remains constant at 48 worker-days.

12 × 4 = 48 worker-days.

Option B: 10 – INCORRECT

Ten workers would require 4.8 days to complete the job under the same working conditions.

10 × 4.8 = 48 worker-days.

This is longer than the required 4 days.

Option C: 6 – INCORRECT

Six workers would require 8 days to complete the same job.

6 × 8 = 48 worker-days.

Reducing the number of workers increases the time needed to finish the job. Therefore, 6 workers cannot complete the task within the required 4 days.

Option D: 14 – INCORRECT

Fourteen workers would require approximately 3.43 days to finish the job.

Although this is sufficient to finish within 4 days, it is more workers than necessary. The question asks for the number of workers needed to complete the job in exactly 4 days under the given assumptions.

Key Mathematical Concepts to Remember

1. Inverse Proportion

Inverse proportion occurs when two quantities change in opposite directions while their product remains constant.

For example, when the number of workers increases, the number of days required to complete a fixed amount of work decreases, provided that the workers have equal productivity.

2. Direct Proportion

Direct proportion occurs when two quantities increase or decrease together at a constant rate.

For example, if one notebook costs P20, buying more notebooks at the same price per notebook increases the total cost proportionally.

3. Worker-Days

Worker-days represent the amount of work completed by a given number of workers over a specified number of days, assuming consistent working hours and productivity.

The formula is:

Total Work = Number of Workers × Number of Days

This formula is useful for solving problems involving workers, time, and a fixed amount of work.

4. Important Assumptions

These problems generally assume that:

  • All workers have equal productivity.
  • Each worker works the same number of hours per day.
  • The amount of work remains constant.
  • There are no significant interruptions or changes in working conditions.

Real-Life Application

Suppose four workers can paint a classroom in eight days. The school administration wants the same painting job completed in four days.

How many workers are needed?

Step 1: Calculate the total worker-days.

4 × 8 = 32 worker-days.

Step 2: Divide by the required completion time.

32 ÷ 4 = 8 workers.

Answer: 8 workers.

This illustrates inverse proportion: reducing the completion time by half requires twice as many workers, assuming equal productivity.

LET Examination Tips

When answering Mathematics questions involving work problems, follow these strategies:

  • Identify the original time. Determine how many days are initially required.
  • Calculate the new time. Pay attention to expressions such as earlier, later, faster, or slower.
  • Identify the relationship. For a fixed amount of work and equal productivity, workers and days are inversely proportional.
  • Use the worker-days formula. Multiply workers by days to obtain the total work.
  • Check your answer. More workers should generally mean fewer days for the same job.

Memory Aid

INVERSE PROPORTION:

More workers = Fewer days.

Fewer workers = More days.

Remember the formula:

Workers × Days = Total Work

For this problem:

8 × 6 = 12 × 4

48 = 48

Frequently Asked Questions

1. What is inverse proportion in Mathematics?

Inverse proportion is a relationship between two quantities in which an increase in one quantity results in a decrease in the other, while their product remains constant.

2. How do you solve workers and days problems?

Multiply the original number of workers by the original number of days to determine the total worker-days. Divide the result by the required number of days to calculate the new number of workers.

3. What is the difference between direct and inverse proportion?

In direct proportion, two quantities increase or decrease together. In inverse proportion, one quantity increases while the other decreases, assuming the relationship remains constant.

Prepare for Your LET / LEPT with St. Louis Review Center!

FREE ONLINE REVIEWER

Strengthen your knowledge through practice questions, answer rationales, and continuous review.

Access the SLRC Free Online Reviewer here:

ACCESS FREE REVIEWER

SLRC — Board Exams Made Easy.

Related Review Resources

Final Encouragement for Future LPTs

Every Mathematics problem you solve strengthens your ability to think logically and make sound decisions. Do not be afraid of word problems. Identify the given information, understand the mathematical relationship, and apply the correct formula.

Continue practicing and developing your problem-solving skills. Your journey toward becoming a licensed professional teacher is worth every effort.